Wastewater System Improvements Meeting
WEEKLY MEETING AGENDA
Town of Cascade
August 28, 2024 – 11:00 AM
Project: Wastewater System Improvements
GWE Project No.: 1-20163-TO4
DISCUSSION
- Open Meeting and Attendance
▪ Town of Cascade:
▪ Great West Engineering:
▪ Ed Boland Construction:
▪ Subcontractors:
▪ Funding Agencies:
- Comments on Previous Meeting Minutes
▪
- Construction Progress/Schedule from Contractor
▪
- RFI’s
▪
- Submittals
▪
- Field Changes and or Field Directives
▪ Discovery of differing manhole elevations – Manhole grade rings likely required for 12 manholes that have already been delivered to site
▪ 10” CIPP on Russell Drive (plans called for 8”)
- Change Orders
▪
- Testing/Quality Control
▪ Compaction Testing – Paul to test with nuclear densometer
- Progress Payments / Pay Request Schedule of Values Review
▪
- Grant Administration/Certified Payroll
▪ Please submit Certified Payroll and Labor Compliance Documentation to Kasia Little – klittle@greatwesteng.com
- Other Issues/General Discussion
▪ Housekeeping
»
▪ Hours of work
» Current work hours are from 7:30am to 5:30 pm, working Monday – Thursday
▪ Hazards and risks
» Obey speed limits in equipment and vehicles.
» Traffic control needs to be in place
▪ Quality of work and standards
»
▪ Access and site concerns
»
▪ Other
»
▪ Establish the Date and Time of the Next Meeting » Wednesday, September 4th at 9:00 AM
▪ Site Visit (if necessary)